GRI-1937: native server install also installs poppler-utils #152

Merged
vivy merged 1 commit from fix/GRI-1937-native-poppler into dev 2026-11-13 13:49:57 +00:00
Owner

The native server install (and so reinstall and upgrade) now installs poppler-utils. Without it a PDF upload fails with pdftoppm is not installed. The Docker image already had it.

Found on the test VM, GRI-1937.

The native server install (and so `reinstall` and `upgrade`) now installs `poppler-utils`. Without it a PDF upload fails with *pdftoppm is not installed*. The Docker image already had it. Found on the test VM, GRI-1937.
GRI-1937: native server install also installs poppler-utils
Some checks failed
CI / the pre-push hook (pull_request) Successful in 11s
CI / cargo fmt (pull_request) Successful in 11s
CI / cargo deny advisories (pull_request) Failing after 1m41s
CI / cargo clippy (pull_request) Successful in 1m53s
CI / cargo deny (pull_request) Successful in 1m46s
CI / repository boundary (pull_request) Successful in 20s
CI / frontend-web (pull_request) Successful in 1m24s
CI / cargo test (pull_request) Successful in 4m13s
CI / Notify gate failed (pull_request) Has been skipped
CI / CI (pull_request) Successful in 22s
d36e62c338
The server shells out to pdftoppm for PDF uploads. The container image
installs poppler-utils; the native path (install, reinstall, upgrade) did
not, so a PDF upload failed with 'pdftoppm is not installed'.
vivy merged commit f8f4d25652 into dev 2026-11-13 13:49:57 +00:00
vivy deleted branch fix/GRI-1937-native-poppler 2026-11-13 13:49:58 +00:00
Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set

Reference
Grimoirix/grimoire-of-digital-signage!152
No description provided.