GRI-1856: defer AC-2-12, AC-3-02, AC-5-07 past the MVP #111

Merged
vivy merged 1 commit from docs/GRI-1856-defer-post-mvp-acceptance-criteria into dev 2026-11-10 17:08:42 +00:00
Member

Marks AC-2-12 (per-IP pending cap), AC-3-02 (background conversion job + progress), and AC-5-07 (offline grace period) as deferred past the MVP in plan/tests/mvp-acceptance.md, per the CTO's decision on signage #29 comment #9859. Each needs a design decision not in the GRI-1761 scope table, so no test is written for them yet. Rows stay in the tables above for traceability; only the new section is added.

Test plan

  • ./scripts/local-gates.sh passed locally (cargo clippy/deny/fmt/test, npm ci, frontend-web check+build).
Marks AC-2-12 (per-IP pending cap), AC-3-02 (background conversion job + progress), and AC-5-07 (offline grace period) as deferred past the MVP in `plan/tests/mvp-acceptance.md`, per the CTO's decision on [signage #29 comment #9859](https://git.grimoirix.org/Grimoirix/grimoire-of-digital-signage/issues/29#issuecomment-9859). Each needs a design decision not in the GRI-1761 scope table, so no test is written for them yet. Rows stay in the tables above for traceability; only the new section is added. ## Test plan - `./scripts/local-gates.sh` passed locally (cargo clippy/deny/fmt/test, npm ci, frontend-web check+build).
GRI-1856: defer AC-2-12, AC-3-02, AC-5-07 past the MVP
Some checks failed
CI / the pre-push hook (pull_request) Successful in 7s
CI / cargo fmt (pull_request) Successful in 7s
CI / cargo clippy (pull_request) Successful in 10m18s
CI / cargo deny (pull_request) Successful in 42s
CI / cargo test (pull_request) Successful in 11m14s
CI / cargo deny advisories (pull_request) Failing after 52s
CI / repository boundary (pull_request) Successful in 7s
CI / frontend-web (pull_request) Successful in 10m1s
CI / Notify gate failed (pull_request) Has been skipped
CI / CI (pull_request) Successful in 3s
c834073c94
vivy merged commit cd02e964a0 into dev 2026-11-10 17:08:42 +00:00
vivy deleted branch docs/GRI-1856-defer-post-mvp-acceptance-criteria 2026-11-10 17:08:43 +00:00
Sign in to join this conversation.
No reviewers
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set

Reference
Grimoirix/grimoire-of-digital-signage!111
No description provided.